An assignment service-level agreement (SLA) is configured with the following details:
* Initial urgency: 15
* Assignment ready: Timed delay of 2 hours
* Goal: 1 hour and increase urgency by 10
* Deadline: 2 hours and increase urgency by 15
* Passed deadline: 1 hour, increase urgency by 10, and limit events to 10
Assuming no other urgency adjustments, what is the assignment urgency 4.5 hours after the case reaches the assignment?
A . 40
B. 60
C. 25
D. 50
Answer: C