Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
A . It is calculated using the original logic.
B . It is calculated using logic reflecting out-of-sequence progress.
C . An out-of-sequence activity cannot resume until all predecessors are finished.
D . There is no such thing.

Answer: B