During what time period is the software configuration management plan implemented?
- A . From the requirements phase through the maintenance phase of the software lifecycle
- B . After the software product is placed into production
- C . From the requirements phase through the testing phase of the software lifecycle
- D . During the code generation phase of the lifecycle
Which of the following is a responsibility of a lead auditor?
- A . Submitting the audit report
- B . Determining the scope of the audit
- C . Determining the corrective actions required
- D . Performing the initial review of the quality system
A company uses a feature rating system with the following values.
1 = Completely dissatisfied
2 = Somewhat dissatisfied
3 = Neither satisfied nor dissatisfied
4 = Somewhat satisfied
5 = Completely satisfied
This rating system is based on what type of measurement scale?
- A . Nominal
- B . Ordinal
- C . Interval
- D . Ratio
Which of the following benefits is related to DevOps when it is used to facilitate development activities?
- A . Reducing time to market
- B . Minimizing software releases
- C . Increasing return on investment
- D . Standardizing organizational processes
At what point in the development lifecycle should change control be implemented?
- A . During the requirements phase
- B . During the implementation phase
- C . At the beginning of the design phase
- D . When the testing phase begins
Which of the following steps comes first during release planning for waterfall-type projects?
- A . Define the scope of the software being developed.
- B . Determine which problems will be corrected in the next release.
- C . Select the set of requirements that will be included in the release.
- D . Confirm the implemented software meets the specified requirements.
Which of the following actions can a company take to reduce the risk associated with integrating a commercial off-the-shelf (COTS) spreadsheet package into its own software product?
- A . Require the vendor to adhere to the keens mg agreement for product fixes.
- B . Audit the vendor’s quality- system.
- C . Require the vendor to place the object code into escrow.
- D . Test the product to determine whether it satisfies critical functions.
The following graph depicts errors per 1,000 lines of code (KLOC) for modules S, T, U, and V.
The program manager should be most concerned about which module?
- A . S
- B . T
- C . U
- D . V
To increase the likelihood of the success of a software project, the project plan should meet which of the following requirements?
- A . It should be completed before the project activities begin.
- B . It should be reviewed and updated at each phase of the project.
- C . It should be developed by an independent software developer
- D . It should be approved by the steering committee.
In the archival process, retention of historical records is
- A . not required
- B . set for at least 2 years
- C . needed for all documents