Site icon Exam4Training

As a team facilitator, what should the project manager do to avoid this?

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams.

As a team facilitator, what should the project manager do to avoid this?
A . Identify the problem’s root causes and define the ground rules with all project team members to minimize interferences
B . Hire a coach to help all project teams to improve their abilities to solve problems on their own.
C . Reunite with the project team members affected and tell them not to reduce the team’s capacity
D . Recommend to the project team members that they should improve their planning and make their stones smaller

Answer: A