As a manager, what is the best way to proceed?

You are a manager at an organization that develops software for customers. The head of product delivery has asked you to provide a plan and schedule for what will be delivered for the upcoming 2

years.

As a manager, what is the best way to proceed?
A . Provide a plan based on your current knowledge and ask the Scrum Teams to implement it.
B. Work with the Product Owners to analyze current goals and delivery capabilities of the teams and create a forecast based on the data to illustrate what might be achievable.
C. Work with the technical architect and technical leads to estimate the plan using a Gantt chart.
D. Ask the Developers to estimate the work for that timeframe in Story Points.

Answer: B

Explanation:

Through empiricism, work with the POs to forecast what could be achievable in the future.