Architects are typically accountable for which measures at the end of the PI?

Architects are typically accountable for which measures at the end of the PI?
A . ART velocity and predictability
B . Business value scores of Enabler Features and Capabilities
C . Return of Investment of delivered Architectural Runway
D . Architectural compliance metrics

Answer: B

Explanation:

Business value scores of Enabler Features and Capabilities