Architects are typically accountable for which measures at the end of the PI?
A . ART velocity and predictability
B . Business value scores of Enabler Features and Capabilities
C . Return of Investment of delivered Architectural Runway
D . Architectural compliance metrics
Answer: B
Explanation:
Business value scores of Enabler Features and Capabilities
Latest SAFe-Architect Dumps Valid Version with 122 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund