Was this an appropriate application of the Five Case Model for this project?
Using the Scenario, answer the following questions about scoping the proposal and preparing the Strategic Outline Case for the Pittville project. Decide whether the approach is appropriate for stage 1, and select the response that supports your decision. When preparing the Strategic Outline Case, the need to address the number...
Should the service scope and underlying assumptions be amended?
Answer the following questions about the actions taken when preparing the Economic Case within the Full Business Case (FBC). The Outline Business Case (OBC) was based on the following preferred way forward: Decide whether the action taken represents an appropriate application of the Five Case Model for this project and...
Is this approach appropriate for defining the spending objectives in the Strategic Outline Case?
The Consortium has stated that within the next three years, it expects to see at least a 15% increase in the attainment of qualifications. However, it has not proposed ways in which the success rates for qualifications can be increased. Is this approach appropriate for defining the spending objectives in...
Which 2 statements should be recorded under the Required services heading?
Using the Scenario, answer the following questions about the Commercial Case for the Pittville project. The following questions include only true statements about the project, but only two statements are appropriate entries for the suggested heading of the Commercial Case. Remember to select 2 answers to each question. Which 2...
Should Economic Appraisals be prepared for the best and final offers for the discarded service providers on the short list?
The best and final offers have been returned for the delivery of the new campus. The preferred supplier was Piaffeco, which was the same supplier that delivered the neighbouring Marshgate High School. Should Economic Appraisals be prepared for the best and final offers for the discarded service providers on the...
Which detail should be explained in the Commercial Case?
Which detail should be explained in the Commercial Case?A . Implementation timescales agreed for delivery.B . Impact on the organization's income and expenditure account.C . Impact on the organization's balance sheet.D . Overall affordability and funding arrangements for the deal.View AnswerAnswer: A
Which 2 attributes demonstrate that this option supports the key CSF Supply-side capacity and capability?
Which 2 attributes demonstrate that this option supports the key CSF Supply-side capacity and capability?A . The campus is to be run by Pittville University but there is stakeholder resistance.B . The new campus will have the space to extend the number of education courses as student numbers increase.C ....
Which 2 attributes demonstrate that this option supports the key CSF Potential value for money?
Which 2 attributes demonstrate that this option supports the key CSF Potential value for money?A . New opportunities will be available for teachers to be involved in delivering the new education courses.B . The 'BAU/status quo' option is the baseline for assessing value for money.C . There is a reasonably...
Which detail should be explained in the Financial Case?
Which detail should be explained in the Financial Case?A . Accountancy treatment of the negotiated deal.B . Explanation of any personnel implications.C . Contingency arrangement for overspends.D . Payment premiums for risk transfer.View AnswerAnswer: A
Should the responsibilities for the benefits realization arrangements be documented in the Economic Case?
The Local Education Authority Director has agreed to be the Senior Responsible Owner. Therefore, they are ultimately responsible for the realization of benefits resulting from the Pittville project. Should the responsibilities for the benefits realization arrangements be documented in the Economic Case?A . No, because the benefits realization arrangements are...