According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?A . During evolutionary development B. At the start of the project C. When the Business Advisor is available D. Whenever the level of solution quality is known.View...
How does DSDM differ from most other Agile approaches?
How does DSDM differ from most other Agile approaches?A . It focuses on the entire project lifecycle B. It focuses on the development of products C. It focuses on the delivery of products D. It focuses on the collaborative working of teamsView AnswerAnswer: A
Principles 1 CFocus on the Business Need suggests that every decision taken during a project should be [?
Identify the missing words in the following sentence. Principles 1 CFocus on the Business Need suggests that every decision taken during a project should be [?] C to deliver what the business needs to be delivered.A . The responsibility of the Business Sponsor B. Share between all of the project...
When is a Timebox Plan updated?
When is a Timebox Plan updated?A . At the Daily Start-ups B. At Timebox Kick-ups C. As needed by the Project Manager D. Each time a Timebox is completedView AnswerAnswer: D
In a free format Timebox, when should reviews take place?
In a free format Timebox, when should reviews take place?A . During the Kick-Off phase B. Throughout the body of the Timebox. C. During the Close.Out phase D. After the Timebox has been completedView AnswerAnswer: B