In a free format Timebox, when should reviews take place?
In a free format Timebox, when should reviews take place?A . During the Kick-Off phase B. Throughout the body of the Timebox. C. During the Close.Out phase D. After the Timebox has been completedView AnswerAnswer: B
Principles 1 CFocus on the Business Need suggests that every decision taken during a project should be [?
Identify the missing words in the following sentence. Principles 1 CFocus on the Business Need suggests that every decision taken during a project should be [?] C to deliver what the business needs to be delivered.A . The responsibility of the Business Sponsor B. Share between all of the project...
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?A . Business Analyst B. Workshop Facilitator C. Business Ambassador D. Business VisionaryView AnswerAnswer: B
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?A . Foundation Summary B. Delivery Plan C. Terms of Reference D. Management Approach DefinitionView AnswerAnswer: A
Which purpose relates to the Consolidation in a structured Timebox?
Which purpose relates to the Consolidation in a structured Timebox?A . To confirm the detail of all the requirements to be delivered by the structured Timebox. B. To address the requirements and test the structure Timebox product. C. To formality accept the structured Timebox deliverables. D. To tie up any...
How should DSDM team measure progress?
How should DSDM team measure progress?A . Through a project dashboard B. Based on what has been delivered at the end of a Timebox. C. Based on the completion of activities rather than the delivery of products D. Through an analysis of the Instrumental Success Factors.View AnswerAnswer: B
Which of the following is NOT an interest into which each DSDM role is grouped?
Which of the following is NOT an interest into which each DSDM role is grouped?A . Business B. Solution/Technical C. Management D. MaintenanceView AnswerAnswer: C
Which of the following is a DSMD principle?
Which of the following is a DSMD principle?A . Build incrementally from firm foundations B. Build incrementally from Feasibility onwards C. Build incrementally in Timeboxes D. Build incrementallyView AnswerAnswer: A
When initially creating MoSCoW priorities, what is the primary focus?
When initially creating MoSCoW priorities, what is the primary focus?A . Project priorities B. Project increment priorities C. Timebox priorities D. Iterative Development prioritiesView AnswerAnswer: A
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?A . During evolutionary development B. At the start of the project C. When the Business Advisor is available D. Whenever the level of solution quality is known.View...