Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
- A . Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox’s deliverable as a whole, in order to keep focus on the business need.
- B . Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.
- C . No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements’ acceptance criteria, with nothing extra.
- D . No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
- A . Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox’s deliverable as a whole, in order to keep focus on the business need.
- B . Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.
- C . No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements’ acceptance criteria, with nothing extra.
- D . No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
- A . Chief Executive (Steering Group)
- B . Representative for Earth Excavations (Solution Developer)
- C . Representative for Timber Tigers (Solution Developer)
- D . IT Operations Manager (Solution Development Team)
- E . Marketing Director (Business Visionary)
Which 2 individuals would be suitable for the role of Workshop Facilitator?
- A . Team Leader
- B . IT Operations Manager
- C . Marketing Director
- D . Software Developer
- E . Project Manager
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
- A . Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.
- B . Invite the Marketing Director to create a summary of the content they believe the system should hold and why.
- C . Assign ownership of the workshop to the Software Developer.
- D . Ask the IT Operations Manager to prepare the agenda for the workshop.
- E . Research other hotel reservation systems to form an opinion on what the content should be.
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
- A . Hints and tips on how to influence and persuade others.
- B . An understanding of the decision-making process.
- C . Background to the disagreement and the reasons for this.
- D . Empowerment to discuss any wider project issues that may arise during the workshop.
- E . A step-by-step guide to running an effective workshop.
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
- A . Present own interpretation of what the system should include.
- B . Present the group with a predefined specification of what should be included.
- C . Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.
- D . Agree to disagree, and close the workshop acknowledging that all participants are entitled to their
own view. - E . Prepare a report describing the outcome of the workshop.
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
- A . Present own interpretation of what the system should include.
- B . Present the group with a predefined specification of what should be included.
- C . Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.
- D . Agree to disagree, and close the workshop acknowledging that all participants are entitled to their
own view. - E . Prepare a report describing the outcome of the workshop.
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
- A . Present own interpretation of what the system should include.
- B . Present the group with a predefined specification of what should be included.
- C . Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.
- D . Agree to disagree, and close the workshop acknowledging that all participants are entitled to their
own view. - E . Prepare a report describing the outcome of the workshop.
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
- A . Present own interpretation of what the system should include.
- B . Present the group with a predefined specification of what should be included.
- C . Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.
- D . Agree to disagree, and close the workshop acknowledging that all participants are entitled to their
own view. - E . Prepare a report describing the outcome of the workshop.