Which statement applies to the DSDM process?
- A . Can be configured and calibrated to cater for light or strong governance
- B . DSDM projects can deliver the phases in the DSDM process in any order
- C . Does not require the elaboration of supporting products for complex projects
- D . Provides an approach that can be used for all projects without change
When initially creating MoSCoW priorities, what is the primary focus?
- A . Project priorities
- B . Project increment priorities
- C . Timebox priorities
- D . Iterative Development priorities
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
- A . During evolutionary development
- B . At the start of the project
- C . When the Business Advisor is available
- D . Whenever the level of solution quality is known.
In a free format Timebox, when should reviews take place?
- A . During the Kick-Off phase
- B . Throughout the body of the Timebox.
- C . During the Close.Out phase
- D . After the Timebox has been completed
Which of the following is a DSMD principle?
- A . Build incrementally from firm foundations
- B . Build incrementally from Feasibility onwards
- C . Build incrementally in Timeboxes
- D . Build incrementally
When should the quality of the evolving solution first be tesed?
- A . At the end of a Timebox
- B . At the end of a project.
- C . At the end of each increment
- D . As part of the iterative Development process
When is a Timebox Plan updated?
- A . At the Daily Start-ups
- B . At Timebox Kick-ups
- C . As needed by the Project Manager
- D . Each time a Timebox is completed
Identify the missing words in the following sentence.
Principles 1 CFocus on the Business Need suggests that every decision taken during a project should be [?] C to deliver what the business needs to be delivered.
- A . The responsibility of the Business Sponsor
- B . Share between all of the project roles
- C . Viewed in light of the overriding project goal
- D . Made collaboratively
Which purpose relates to the Consolidation in a structured Timebox?
- A . To confirm the detail of all the requirements to be delivered by the structured Timebox.
- B . To address the requirements and test the structure Timebox product.
- C . To formality accept the structured Timebox deliverables.
- D . To tie up any loose ends related to Evolutionary Development
Which of the following is NOT an interest into which each DSDM role is grouped?
- A . Business
- B . Solution/Technical
- C . Management
- D . Maintenance