How can integrating sustainability principles and priorities into the management of this project positively impact its long-term success?
A construction company is planning to build a new office complex. The project manager is considering integrating sustainability principles and priorities into the project management process. How can integrating sustainability principles and priorities into the management of this project positively impact its long-term success? By fostering innovation and creativity, leading...
What type of risk response would you choose to mitigate this risk?
You are leading a large-scale information technology project to migrate your company’s data to the latest hardware. The delivery is being led by third-party suppliers, who were not involved in the design phase. The supplier has completed their capacity planning and has raised a potential risk that the current data...
According to Herzberg's two-factor theory, which of the following best illustrates a leader who positively impacts team performance and motivation?
According to Herzberg's two-factor theory, which of the following best illustrates a leader who positively impacts team performance and motivation?A . A leader who fosters a collaborative work environment and recognizes individual achievements.B . A leader who maintains a positive stance on work conditions and refrains from team member engagement...
You are managing a project to develop and deploy a new finance management software system for a client. The project has been deployed and is now in the post-deployment support phase. This phase requires ongoing technical support and maintenance after the software is deployed. The workload can vary significantly over time, is likely to evolve over time, and quick response times are essential. Question: Based on the features of different contractual relationships and methods of supplier reimbursement, state the most appropriate contract type for the post-deployment phase
SIMULATION You are managing a project to develop and deploy a new finance management software system for a client. The project has been deployed and is now in the post-deployment support phase. This phase requires ongoing technical support and maintenance after the software is deployed. The workload can vary significantly...
Which life cycle would be most suitable?
You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project. Which life cycle would be most suitable?A . IterativeB . HybridC . IncrementalD . LinearView AnswerAnswer:...
Which factor should NOT influence your decision when assigning roles and responsibilities to your team members?
You are a project manager leading a newly formed project team. Which factor should NOT influence your decision when assigning roles and responsibilities to your team members?A . Project management qualifications.B . Relevant industry experience.C . Preferred communication style.D . Number of years in post.View AnswerAnswer: D Explanation: Why It’s...
You are appointed as project manager on a major project that started several months earlier. The project has many diverse stakeholders, and you discover that a stakeholder communications plan has not been completed
SIMULATION You are appointed as project manager on a major project that started several months earlier. The project has many diverse stakeholders, and you discover that a stakeholder communications plan has not been completed. State two possible negative effects of not having an effective stakeholder communications plan for the project:View...