Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?

Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?A . Linear project life cycles set the deployment baseline for the whole project.B . In an iterative project life cycle the scope and quality are fixed in the deployment baseline.C . Only...

August 13, 2024 No Comments READ MORE +

Project risk management is best described as:

Project risk management is best described as:A . managing responses to threats.B . identifying and acknowledging threats and opportunities.C . planning responses to threats.D . minimising threats and maximising opportunities.View AnswerAnswer: D

August 13, 2024 No Comments READ MORE +

Which of the following is the correct sequence for the stages of a linear project life cycle?

Which of the following is the correct sequence for the stages of a linear project life cycle?A . Deployment, Concept, Definition, Transition.B . Concept, Transition, Definition, Deployment.C . Concept, Definition, Deployment, Transition.D . Transition, Definition, Deployment, ConceptView AnswerAnswer: C

August 13, 2024 No Comments READ MORE +

Who owns the Project Management Plan (PMP)?

Who owns the Project Management Plan (PMP)?A . The project team.B . The chief executive.C . The project manager.D . The project support officeView AnswerAnswer: B

August 13, 2024 No Comments READ MORE +

Which of these is not part of the linear project life cycle?

Which of these is not part of the linear project life cycle?A . ConceptB . DefinitionC . OperationsD . TransitionView AnswerAnswer: C

August 13, 2024 No Comments READ MORE +

Which project management process is NOT likely to be used when resolving an issue?

Which project management process is NOT likely to be used when resolving an issue?A . Risk managementB . Change controlC . Scope managementD . Team buildingView AnswerAnswer: D

August 12, 2024 No Comments READ MORE +

Which one of the following statements BEST defines procurement?

Which one of the following statements BEST defines procurement?A . A technique to establish the best approach for obtaining the resources for the projectB . A group of interrelated resources and activities that transform inputs into outputsC . The description of the purpose, form and components to support delivery of...

August 11, 2024 No Comments READ MORE +

Which of the following BEST describes a project issue?

Which of the following BEST describes a project issue?A . An event that may or may not occurB . An opportunity that occurs through change controlC . A problem that the project manager has to deal with on a day-to-day basisD . A problem that must be escalated to the...

August 11, 2024 No Comments READ MORE +

The purpose of a decision gate is to decide whether:

The purpose of a decision gate is to decide whether:A . the response to a risk is valid.B . a project is viable in line with the business case.C . the project delivered against the success criteria.D . lessons were effectively learned during the project.View AnswerAnswer: B

August 11, 2024 No Comments READ MORE +

Which of the following defines the term 'deployment baseline'?

Which of the following defines the term 'deployment baseline'?A . The starting point for creating a resource histogram.B . The basis for creating an organisational breakdown structure.C . The starting point for the monitoring of project risks.D . The basis for progress monitoring.View AnswerAnswer: D

August 11, 2024 No Comments READ MORE +