A communication management plan identifies the relevant information that should be communicated to:

A communication management plan identifies the relevant information that should be communicated to:A . the project team.B . the project stakeholders.C . the project board.D . the project sponsorView AnswerAnswer: B

August 19, 2024 No Comments READ MORE +

One purpose of risk management is to:

One purpose of risk management is to:A . adapt the plan to resolve problems.B . minimise threats and maximise opportunities.C . continually improve the project teams' efficiency.D . manage variations in a controlled wayView AnswerAnswer: A

August 18, 2024 No Comments READ MORE +

Which one of the following statements is true?

Which one of the following statements is true?A . An increase in project scope is likely to increase project cost.B . A decrease in the project time is likely to increase project quality.C . An increase in the project quality requirements is likely to decrease project cost.D . A decrease...

August 17, 2024 No Comments READ MORE +

One difference between an issue and a risk is an issue:

One difference between an issue and a risk is an issue:A . must be recorded but a risk does not.B . is an uncertain event but a risk is not.C . is a certain event but a risk is not.D . always affects scope but a risk does notView AnswerAnswer:...

August 17, 2024 No Comments READ MORE +

Suppliers are stakeholders of a project management plan because they:

Suppliers are stakeholders of a project management plan because they:A . contribute to the project's procurement strategy.B . help satisfy the project's resource requirements.C . provide acceptance certificates based on quality of resources supplied.D . determine the quality requirements of goods supplied.View AnswerAnswer: B

August 17, 2024 No Comments READ MORE +

Which of the following is an activity in a typical change control process?

Which of the following is an activity in a typical change control process?A . Recommendation.B . Justification.C . Planning.D . Continuous improvementView AnswerAnswer: A

August 16, 2024 No Comments READ MORE +

Which of these is a key aspect of Programme Management?

Which of these is a key aspect of Programme Management?A . Business as usual reportingB . Strategic directionC . Benefits managementD . Managing the project schedulesView AnswerAnswer: C

August 16, 2024 No Comments READ MORE +

Programme Management can BEST be described as...

Programme Management can BEST be described as...A . the management of multiple projects by one project manager.B . the management of very large, complex projects.C . the means of linking business strategy to projects within an organisation.D . a fashionable term which means the same as Project Management.View AnswerAnswer: C

August 16, 2024 No Comments READ MORE +

Which one of the following statements BEST defines procurement?

Which one of the following statements BEST defines procurement?A . A technique to establish the best approach for obtaining the resources for the projectB . A group of interrelated resources and activities that transform inputs into outputsC . The description of the purpose, form and components to support delivery of...

August 16, 2024 No Comments READ MORE +

The main aim of quality management is to:

The main aim of quality management is to:A . prepare a high-quality management plan.B . ensure that deliverables meet appropriate standards.C . validate the use of consistent standards.D . determine whether to accept change requests.View AnswerAnswer: B

August 16, 2024 No Comments READ MORE +