You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project.
Which life cycle would be most suitable?
- A . Iterative
- B . Hybrid
- C . Incremental
- D . Linear
You are leading a large-scale information technology project to migrate your company’s data to the latest hardware. The delivery is being led by third-party suppliers, who were not involved in the design phase. The supplier has completed their capacity planning and has raised a potential risk that the current data may exceed the storage capacity of the new hardware purchased.
What type of risk response would you choose to mitigate this risk?
- A . Tolerate the risk as there may be sufficient storage capacity.
- B . Re-forecast the budget to include the likely additional cost.
- C . Use the contingency budget to cover the purchase of additional storage.
- D . Transfer the risk to the supplier.
SIMULATION
You are managing a project to develop and deploy a new finance management software system for a client. The project has been deployed and is now in the post-deployment support phase. This phase requires ongoing technical support and maintenance after the software is deployed. The workload can vary significantly over time, is likely to evolve over time, and quick response times are essential. Question: Based on the features of different contractual relationships and methods of supplier reimbursement, state the most appropriate contract type for the post-deployment phase. (1 mark)
Question: Explain four reasons why this would be the most suitable. (4 marks)
Structure is the most common temporary structure used to manage projects. This allows the balance of authority between the functional line manager and the project manager. In a permanent structure, allocated tasks will match an individual’s capability so may be more repetitive and less varied.
- A . Matrix Structure
- B . Functional Structure
- C . Projectized Structure
- D . Hybrid Structure
A construction company is planning to build a new office complex. The project manager is considering integrating sustainability principles and priorities into the project management process.
How can integrating sustainability principles and priorities into the management of this project positively impact its long-term success?
By fostering innovation and creativity, leading to more resilient solutions that adapt to changing environmental and social conditions in the construction of the office complex.
By requiring additional planning and coordination to integrate sustainability measures seamlessly into existing project timelines and workflows, potentially leading to short-term disruptions in scheduling.
By enhancing stakeholder trust and reputation, which can attract investors and clients committed to sustainable practices in the development of the office complex.
By restricting resource consumption and waste generation during the construction process, to guarantee cost savings and improved resource efficiency in this phase of the project. By improving worker safety through sustainable construction practices.
By reducing upfront costs but increasing long-term maintenance expenses due to sustainable building materials.
- A . 3 and 6
- B . 1 and 3
- C . 1 and 5
- D . 2 and 4
During a project review, which of the following would be the best indicator of how the project outputs are progressing?
- A . Earned value – tracking spend to assess delivery progress.
- B . Benefits realisation – tracking whether the project has achieved the business case.
- C . Resource management – tracking whether the project team is meeting utilisation targets.
- D . Budget tracking – monitoring actual spend against planned spend.
SIMULATION
You have been assigned to manage a new project team. The team has recently been set up to improve service levels which have drastically reduced over the past year.
Only a few of the team members have worked together before. It is your responsibility as the leader to facilitate the team’s development.
Question: Identify two models you could use to facilitate developing your team. (2 marks)
Question: Explain three ways team development models can help the team meet their objective to improve service levels. (3 marks)
SIMULATION
You are appointed as project manager on a major project that started several months earlier. The project has many diverse stakeholders, and you discover that a stakeholder communications plan has not been completed.
State two possible negative effects of not having an effective stakeholder communications plan for the project:
According to Herzberg’s two-factor theory, which of the following best illustrates a leader who positively impacts team performance and motivation?
- A . A leader who fosters a collaborative work environment and recognizes individual achievements.
- B . A leader who maintains a positive stance on work conditions and refrains from team member engagement to allow productivity.
- C . A leader who monitors every task and provides guidelines for completing them.
- D . A leader who refrains from situational feedback but offers opportunities for career advancement.
You are a project manager leading a newly formed project team.
Which factor should NOT influence your decision when assigning roles and responsibilities to your team members?
- A . Project management qualifications.
- B . Relevant industry experience.
- C . Preferred communication style.
- D . Number of years in post.