Question #81
The purpose of a risk register is to provide a:
- A . structured process for risk identification.
- B . record of the ownership of risk and issue management actions.
- C . means of assessing the likelihood and impact of all of the risks.
- D . record of risks, their impact and the actions taken to manage them.
Question #82
Which of the following is a part of change control?
- A . Requests for change are realised.
- B . Requests for change are mitigated.
- C . Requests for change are evaluated.
- D . Requests for change are resolved.
Question #83
The primary purpose of a milestone in a project is to show:
- A . significant events.
- B . resource constraints.
- C . task dependencies.
- D . critical path highlights.
Question #84
Which of the following can be adjusted during a time box? 1) Scope 2) Resource 3) Time 4) Quality
- A . 1 and 2 only
- B . 1 and 4 only
- C . 3 and 4 only
- D . 2 and 4 only
Question #85
A communication management plan identifies the relevant information that should be communicated to:
- A . the project team.
- B . the project stakeholders.
- C . the project board.
- D . the project sponsor
Question #86
Which one of the following statements is true?
- A . Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.
- B . Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.
- C . Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.
- D . Quality planning enables the project manager to manage the trade-off between customer expectations and budget.
Question #87
Project risk management is best described as:
- A . managing responses to threats.
- B . identifying and acknowledging threats and opportunities.
- C . planning responses to threats.
- D . minimising threats and maximising opportunities.
Question #88
Which one of the following best describes a project issue?
- A . A major problem that requires formal escalation.
- B . A problem that the project manager has to deal with on a day-to-day basis.
- C . An uncertain event that may or may not occur.
- D . An opportunity that occurs through change control.
Question #89
Scheduling can best be defined as the process used to determine:
- A . overall project duration.
- B . project cost estimating.
- C . the project management plan.
- D . sub-contractor’s responsibilities
Question #90
Which one of the following statements is true?
- A . An increase in project scope is likely to increase project cost.
- B . A decrease in the project time is likely to increase project quality.
- C . An increase in the project quality requirements is likely to decrease project cost.
- D . A decrease in the project cost is likely to decrease project time.