Which of the following is the correct sequence for the stages of a linear project life cycle?
- A . Deployment, Concept, Definition, Transition.
- B . Concept, Transition, Definition, Deployment.
- C . Concept, Definition, Deployment, Transition.
- D . Transition, Definition, Deployment, Concept
At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?
- A . Storming.
- B . Forming.
- C . Norming.
- D . Performing
Which of the following is a definition of project management?
- A . A complex process of supervising and managing the delivery of any time-bound deliverable.
- B . Any change in management techniques in a company that achieves strategic objectives.
- C . The application of processes, methods, knowledge, skills and experience to achieve specific objectives for change.
- D . The coordination of several projects alongside business as usual.
Which of the following defines quality?
- A . The fitness for purpose of outputs and processes.
- B . The value for money of a product.
- C . The satisfaction of the stakeholders.
- D . The thoroughness of the management plan.
Quality control verifies that:
- A . the project follows appropriate processes.
- B . project outputs are delivered on time.
- C . the project follows appropriate governance.
- D . project outputs meet acceptance criteria.
The purpose of a decision gate is to decide whether:
- A . the response to a risk is valid.
- B . a project is viable in line with the business case.
- C . the project delivered against the success criteria.
- D . lessons were effectively learned during the project.
Establishing success criteria is important at the start of the project, as they:
- A . indicate how the stakeholder needs will be met.
- B . ensure adequate resource allocation.
- C . indicate what is important in supplier selection.
- D . ensure comprehensive risk analysis.
One purpose of risk management is to:
- A . adapt the plan to resolve problems.
- B . minimise threats and maximise opportunities.
- C . continually improve the project teams’ efficiency.
- D . manage variations in a controlled way
Which of the following is an activity in a typical risk management process?
- A . Verification.
- B . Request.
- C . Closure.
- D . Justification
When an item goes through change control, which of the following must happen as part of a robust configuration management process?
- A . Costs associated with the change are evaluated and documented.
- B . Risks associated with the change are monitored to avoid delays to the project.
- C . The item is approved or declined in line with stakeholder expectations.
- D . Documents are updated to include any approved changes.