Which of the following is not a key element of project scope management?
- A . Define outputs.
- B . Identify outputs.
- C . Share outputs.
- D . Control outputs
Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?
- A . Linear project life cycles set the deployment baseline for the whole project.
- B . In an iterative project life cycle the scope and quality are fixed in the deployment baseline.
- C . Only deployment baselines in iterative life cycles have an integrated baseline review.
- D . Only deployment baselines in linear life cycles have an integrated baseline review
Which of the following defines the term ‘risk’?
- A . The potential of a situation or event to impact on the achievement of specific objectives.
- B . A problem that is now or is about to breach delegated tolerances for work on a project or programme.
- C . Scope creep within an uncontrolled project.
- D . The use of estimation to determine costs, resources and activities.
Suppliers are stakeholders of a project management plan because they:
- A . contribute to the project’s procurement strategy.
- B . help satisfy the project’s resource requirements.
- C . provide acceptance certificates based on quality of resources supplied.
- D . determine the quality requirements of goods supplied.
Which of the following defines the term ‘issue’?
- A . A problem which is now or is about to breach delegated tolerances for work on a project or programme.
- B . A problem which occurs on a day-to-day basis which could have an immediate impact on a project.
- C . A problem which has the potential to impact on the achievement of specific project objectives.
- D . A problem which can only be resolved by a project manager and within the project team
Which of the following define leadership?
1) Ability to establish vision and direction
2) Developing team skills that enhance project performance
3) Empowering and inspiring people to achieve success
4) Ability to influence and align others towards a common purpose
- A . 1,2&4
- B . 1,2&3
- C . 2,3&4
- D . 1,3&4
Which of the following are typical estimating methods? 1) Analytical 2) Budgeting 3) Analogous 4) Parametric
- A . 1, 2 and 4
- B . 1, 2 and 3
- C . 1, 3 and 4
- D . 2, 3 and 4
Procurement strategy can be defined as the high-level approach for securing:
- A . stakeholder engagement.
- B . funding for the project.
- C . buy in from the project sponsor.
- D . goods and services required for the project.
Which of the following is not an output of a critical path analysis?
- A . Total and free float.
- B . Earliest start time and latest finish time of activities.
- C . Project completion time.
- D . Cost-benefit analysis.
A project manager would use a cost breakdown structure to produce:
- A . the cost of a do-nothing option.
- B . an analytical estimate.
- C . high-level project costs.
- D . a comparative estimate.