Question #41
The main aim of quality management is to:
- A . prepare a high-quality management plan.
- B . ensure that deliverables meet appropriate standards.
- C . validate the use of consistent standards.
- D . determine whether to accept change requests.
Question #42
Which of the following is a purpose of issue management?
- A . To stop issues occurring within the project.
- B . To address and resolve the issues that occur.
- C . To address and resolve uncertainty.
- D . To reschedule activities to reduce costs
Question #43
Product breakdown structures illustrate the required scope of work by a hierarchical structure itemising the:
- A . components of each product.
- B . budget of each product.
- C . benefits of each product.
- D . risks of each product.
Question #44
The definition of benefits management includes which key activities?
- A . Planning, analysis and integration of project benefits.
- B . Justification, validation and acceptance of project benefits.
- C . Identification, tracking and realisation of project benefits.
- D . Realisation, acceptance and integration of project benefits
Question #45
Which of the following statements about scheduling is false?
- A . Defines the sequence of activities.
- B . Considers work calendars and time contingency.
- C . Provides a baseline for safety considerations.
- D . Quantifies the required resources.
Question #46
Which of the following defines the term ‘deployment baseline’?
- A . The starting point for creating a resource histogram.
- B . The basis for creating an organisational breakdown structure.
- C . The starting point for the monitoring of project risks.
- D . The basis for progress monitoring.
Question #47
Which of the following is an activity in a typical configuration management process?
- A . Evaluation.
- B . Identification.
- C . Registration.
- D . Justification.
Question #48
Stakeholder analysis supports effective stakeholder engagement by:
- A . identifying stakeholders with high levels of power and interest.
- B . ensuring stakeholder acceptance of project deliverables.
- C . justifying the preferred project option to stakeholders.
- D . providing information to all stakeholders.
Question #49
Which of the following is a project?
- A . Introducing a new information technology system.
- B . Operating a national rail network.
- C . Organising ongoing catering in the armed forces.
- D . Managing day-to-day security for senior politicians
Question #50
One purpose of a typical project business case is to:
- A . carry out earned value analysis.
- B . allocate resources to the project.
- C . analyse cost-benefit of the project.
- D . plan project work packages