Which of the following is the responsibility of a project manager?
- A . Ensuring a project is aligned to the organisation’s strategy.
- B . Focusing on project benefits and aligning priorities.
- C . Achieving the project’s success criteria.
- D . Improving process, tools and techniques used in a project
To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis?
- A . Budget.
- B . Stakeholder.
- C . Resource.
- D . Schedule
Which of the following is a responsibility of the project sponsor?
- A . Creating a project cost breakdown structure.
- B . Authoring the project management plan.
- C . Creating a project work breakdown structure.
- D . Owning the project business case.
Portfolio management includes prioritising:
- A . projects and/or programmes that contribute directly to the organisation’s strategic objectives.
- B . projects with exceptionally high returns on investment.
- C . projects and programmes over business as usual.
- D . projects which maximise change over those which maximise investment
Which of the following actions would not help a team leader influence the performance of their team?
- A . Creating an exclusive environment.
- B . Providing clear roles and responsibilities.
- C . Promoting openness and honesty.
- D . Developing a trusting relationship.
One difference between a project and business as usual is:
- A . projects achieve specified benefits but business as usual has only vague benefits.
- B . projects drive change whereas business as usual continues existing activities.
- C . projects have tightly controlled budgets whereas business as usual does not.
- D . projects have unclear deadlines but business as usual has multiple milestones
The purpose of project progress reporting is to:
- A . ensure a simpler critical path.
- B . enable the tracking of project deliverables.
- C . ensure stakeholder acceptance of project deliverables.
- D . provide an increased total float.
Which of the following is the purpose of an estimating funnel?
- A . Keeping resource usage to a minimum to help reduce costs.
- B . Supporting the production of comparative estimates.
- C . Identifying where costs can be minimised when preparing a budget.
- D . Representing increasing levels of estimating accuracy achieved through the life cycle
One advantage of virtual communications is:
- A . that nonverbal signals can have an impact on discussions.
- B . it’s easy to detect signs of conflict within the project team.
- C . access to a wider resource pool for the project.
- D . that the project team will always be co-located.
Which technique could be used by a project manager when resources are limited?
- A . Resource aggregation.
- B . Resource estimation.
- C . Resource levelling.
- D . Resource expansion