APM APM-PFQ APM Project Fundamentals Qualification (PFQ) Online Training
APM APM-PFQ Online Training
The questions for APM-PFQ were last updated at Nov 20,2024.
- Exam Code: APM-PFQ
- Exam Name: APM Project Fundamentals Qualification (PFQ)
- Certification Provider: APM
- Latest update: Nov 20,2024
Question #101
Which one is a true statement relating to project communications?
- A . A project sponsor is responsible for all communication methods and media.
- B . Different stakeholders typically have different communication needs.
- C . It is best to have a standard set of project reports used for every project.
- D . Email is the only way to communicate with large numbers of people.
Question #102
In project management, the term quality is best defined as:
- A . inspection, testing and measurement.
- B . reviews and audits.
- C . fitness for purpose of deliverables.
- D . professionally-bound project reports.
Question #103
The main outcome of risk identification, in a risk management process, is to:
- A . identify and determine the relative importance of the project risks.
- B . identify and describe all risks that might occur on the project.
- C . identify and determine the responses to the project risks.
- D . identify and describe risks that have occurred on previous projects
Question #104
Which one of the following is not considered in resource management?
- A . Identifying resources.
- B . Influencing resources.
- C . Assigning resources to activities.
- D . Matching resources to the schedule.