Question #1
In which phase of the project should the Procurement Strategy be written?
- A . Concept
- B . Definition
- C . Deployment
- D . Transition
Question #2
In developing a network the first task after listing the activities is to…
- A . Define activity durations
- B . Determine float
- C . Determine the interdependencies of activities
- D . Harmonise the activity to a calendar
Question #3
Which of these is a correct definition of an Estimate?
- A . The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work
- B . An educated guess that improves over time
- C . A forecast of the probable time or cost of completing work
- D . An estimate is an approximation of project time and cost targets that forms the basis of the contract
Question #4
Risk management should be initiated…
- A . when the Project Management Plan is initiated.
- B . at the time the Work Breakdown Structure is developed.
- C . at the start of the project.
- D . once the project concept is understood.
Question #5
When are benefits usually realised when using an iterative life cycle?
- A . During the project
- B . Post project
- C . At project closure
- D . Both during and after the project
Question #6
When is an analysis of a project’s environment most likely to be undertaken?
- A . In the Definition Phase
- B . In the Transition Phase
- C . In the Concept Phase
- D . In the Deployment Phase
Question #7
Which one of the following statements BEST defines procurement?
- A . A technique to establish the best approach for obtaining the resources for the project
- B . A group of interrelated resources and activities that transform inputs into outputs
- C . The description of the purpose, form and components to support delivery of a product
- D . The process by which products and services required for the project are acquired
Question #7
Which one of the following statements BEST defines procurement?
- A . A technique to establish the best approach for obtaining the resources for the project
- B . A group of interrelated resources and activities that transform inputs into outputs
- C . The description of the purpose, form and components to support delivery of a product
- D . The process by which products and services required for the project are acquired
Question #7
Which one of the following statements BEST defines procurement?
- A . A technique to establish the best approach for obtaining the resources for the project
- B . A group of interrelated resources and activities that transform inputs into outputs
- C . The description of the purpose, form and components to support delivery of a product
- D . The process by which products and services required for the project are acquired
Question #7
Which one of the following statements BEST defines procurement?
- A . A technique to establish the best approach for obtaining the resources for the project
- B . A group of interrelated resources and activities that transform inputs into outputs
- C . The description of the purpose, form and components to support delivery of a product
- D . The process by which products and services required for the project are acquired