APICS CPIM-8.0 Certified in Planning and Inventory Management (CPIM 8.0) Online Training
APICS CPIM-8.0 Online Training
The questions for CPIM-8.0 were last updated at Feb 18,2025.
- Exam Code: CPIM-8.0
- Exam Name: Certified in Planning and Inventory Management (CPIM 8.0)
- Certification Provider: APICS
- Latest update: Feb 18,2025
A work center has 3 machines that are all run at the same time with a single worker. The work center has an efficiency of 75% and a utilization of 100%.
What is the work center’s capacity in standard hours for an 8-hour shift?
- A . 6 hours
- B . 8 hours
- C . 18 hours
- D . 24 hours
Which of the following benefits typically will be realized when switching from a functional to a cellular layout?
- A . Equipment utilization will be higher.
- B . Quality inspections will be reduced.
- C . Capital expenditures will be reduced.
- D . Products will have faster throughput.
For a process that is outside its upper control limit (UCL), which of the following techniques would best be used to return the process under control?
- A . Conduct a Pareto analysis
- B . Plan-do-check-action (PDCA)
- C . Plot histograms
- D . Monitor control charts
Which of the following statements is an assumption on which the economic order quantity (EOQ) model is based?
- A . Customer demand is known but seasonal.
- B . Items are purchased and/or produced continuously and not in batches.
- C . Order preparation costs and inventory-carrying costs are constant and known.
- D . Holding costs, as a percentage of the unit cost, are variable.
Which of the following capacity planning methods uses the master production schedule (MPS) as its primary input?
- A . Resource planning
- B . Rough-cut capacity planning (RCCP)
- C . Finite loading
- D . Input/output analysis
What activity is a useful element in the change process?
- A . Creating short-term wins
- B . Calculating a break-even point
- C . Performing a SWOT analysis
- D . Developing key performance indicators (KPIs)
The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:
- A . revise the rough-cut capacity plan.
- B . reschedule a related component on the shop floor.
- C . check the accuracy of the bills for the MPS items.
- D . determine if a customer order will be impacted.
A manufacturer has a forecasted annual demand of 1,000,000 units for a new product. They have to choose 1 of 4 new pieces of equipment to produce this product. Assume that revenue will be $10 per unit for all 4 options.
Which machine will maximize their profit if the manufacturer anticipates market demand will be steady for 3 years and there is no residual value for any of the equipment choices?
MachineFixed CostVariable Cost per UnitAnnual Capacity
AS100.000$6 00800,000 units
B$200,000$5 501.000,000 units
C$250,000$5 001,200,000 units
D$1000.000$4 501 400.000 units
- A . Machine A
- B . Machine B
- C . Machine C
- D . Machine D
When designing a production cell, which of the following items would be the most important consideration?
- A . Theunit per hour requirement for the production cell to meet the sales forecast
- B . Theflow of materials into the cell and sequencing of operations to minimize total cycle time
- C . Theoutput rate for the first operation and move time after the last workstation
- D . Thetakt time requirement for each operator to meet the monthly production goals of theplant
Forecast error typically triggers forecast revision when it is:
- A . used in computing the tracking signal.
- B . associated with the Introduction stage of the product life cycle.
- C . continually increasing.
- D . caused by random variation.