During the sales and operations planning (S&OP) process, which of the following tasks is the primary responsibility of the functional representatives on the supply planning team?
- A . Identifying reasons why the demand plan is not realistic
- B . Communicating when an event will prevent meeting the supply plan
- C . Ensuring that the functional objectives are considered when developing the plans
- D . Understanding how to use the plan to improve functional performance
Global outsourcing and shared suppliers serving an industry are drivers of which category of risk?
- A . Supply disruptions
- B . Forecast inaccuracy
- C . Procurement problems
- D . Loss of intellectual property
The primary purpose for engaging in cycle count activities is to:
- A . eliminate the need for a traditional physical inventory count.
- B . more frequently reconcile the actual on-hand and system on-hand for items.
- C . smooth out the tasks of counting inventory throughout the fiscal year.
- D . improve material handling processes and reduce or eliminate errors.
An order winner during the growth stage of a product’s life cycle is:
- A . variety.
- B . availability.
- C . dependability.
- D . price.
Which of the following items does the master scheduler have the authority to change in the master scheduling process?
- A . Product mix
- B . Aggregate volume
- C . Engineering change effectivity date
- D . Customer order quantities
Which of the following prioritization rules will have the greatest impact In reducing the number of orders In queue?
- A . Critical ratio
- B . Shortest processing time
- C . Fewest operations remaining
- D . First come, first served
What priority control technique is most appropriate for a firm using a cellular production system?
- A . Shortest processing time (SPT) rule
- B . Distribution requirements planning (DRP)
- C . Pull production activity control (PAC)
- D . Push production activity control (PAC)
Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?
- A . History shows that the quality level has been stable from lot to lot.
- B . The company uses one of its qualified suppliers.
- C . Downstream operators encounter recurring defects.
- D . The percent of defects is expected to be greater than 5%.
Which of the following systems would be the most cost-efficient for inventory management of a low value item?
- A . Order point
- B . Material requirements planning (MRP)
- C . Periodic review
- D . Economic order quantity (EOQ)
The costs provided in the table below are associated with buying a quantity larger than immediately needed.
What Is the total landed cost based on this table?
Cost CategoryCost
Custom fees$125
Freight$700
Warehouse rent$200
Matenal cost$500
- A . $825
- B . $1,325
- C . $1,400
- D . $1,525