___________is usually not the primaryobjective of a rabiassessment, but it is frequently a side effect of optimization.
- A . Reducing inspection costs
- B . Increasing inspection costs
- C . Increasing frequency of inspection programs
Probability of failure analysis is made from
- A . Loss of containment that occurs due to deterioration mechanism
- B . Consequences of the failure
- C . Done just with previous experience
- D . All the above
If multiple inspections have been performed, which inspection may best reflect current operating conditions?
- A . Most recent inspection
- B . Base line inspection survey
- C . Process conditions
- D . Corrosion survey
The type of failure mode that likely to occur due to mechanical and metallurgical deterioration
- A . Smallholes to ruptures
- B . Cracks
- C . Catastrophic ruptures
- D . Leaks
Hazard identification in a rbi analysis generally focuses on identifiable failure mechanisms in the equipment (inspectable causes) but does not explicitly deal with
- A . Other potential failure scenarios resulting from events such as power S failures or human errors
- B . Other potential failure resulting from events such as flammable fire due to leak from equipment
- C . Environmental impact caused due to toxic release
Reliability efforts, such as reliability centered maintenance (rem), can be linked with rbi, resulting in an integrated program to
- A . Reducedowntime in an operating unit
- B . Reduce operating time of a unit
- C . To reduce risk by mitigation activities
Some failures have potentially serious consequences, but if the probabilityof the incident is low, then
- A . The risk may not warrant immediate action
- B . The risk may warrant immediate action
- C . The risk may warrant appropriate mitigation action
Fora typical inspection program, if excessive inspectionis applied then,
- A . Level of risk may go up
- B . Level of risk may go down
- C . Level of risk remain the same
Act of mitigating a known risk to a lower level of risk.
- A . Risk reduction
- B . Risk mitigation
- C . Risk evaluation
When in accurate or insufficient failure data exists on the specific equipment item for quantative probability of failure analysis then
- A . General industry, company or manufacturer failure data used
- B . Process hazard analysis failure data may be used
- C . Process and toxic concentration analysis may be used