Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:
Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:
A. Activity ID
B. WBS Code
C. Resource
D. Account number
Answer: A
Explanation:
An Activity ID is a unique combination of letters, numbers, or blanks that describes and identifies any activity or task shown on a project schedule. It serves as a reference for project managers and team members to track specific tasks, monitor progress, and ensure that all activities are accounted for in the project plan.
Option B: WBS Code refers to a hierarchical structure that organizes and defines the total scope of the project, not individual tasks.
Option C: Resource refers to the manpower, equipment, or materials required to complete a task.
Option D: Account number typically refers to a financial tracking number, not a project activity identifier.
Therefore, A. Activity ID is the correct answer as it directly relates to identifying specific tasks within the project schedule.