An output of the Develop Project Team process is:
A . change requests
B . team performance assessments
C . project staff assignments
D . project documents updates
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund