Site icon Exam4Training

An output of the Develop Project Team process is:

An output of the Develop Project Team process is:
A . change requests
B . team performance assessments
C . project staff assignments
D . project documents updates

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version