An expediter would be expected to primarily:
A . Undertake purchasing research
B . Deliver in-house procurement training
C . Chase up late or potentially late deliveries
D . Pay invoices
Answer: C
Explanation:
Chase up late or potentially late deliveries – a task which in an ideal procurement world, would be unnecessary. I am hoping that ‘in the real world’ the volume of this type of activity is in decline.