An expediter would be expected to primarily:

An expediter would be expected to primarily:
A . Undertake purchasing research
B . Deliver in-house procurement training
C . Chase up late or potentially late deliveries
D . Pay invoices

Answer: C

Explanation:

Chase up late or potentially late deliveries – a task which in an ideal procurement world, would be unnecessary. I am hoping that ‘in the real world’ the volume of this type of activity is in decline.

Latest L3M4 Dumps Valid Version with 90 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments