After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:

After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:
A . Level of authority and level of interest
B . Level of authority and level of involvement
C . Level of influence and level of impact
D . Level of influence and level of interest

Answer: D