After getting more information about the new manager, what is the project manager’s next step?

In the middle of a project, a business unit manager who regularly interacts with the project manager’s team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager’s next step?
A . Contact the previous business unit manager to learn more about the new manager.
B . Update the stakeholder register and the stakeholder engagement plan to include the new manager.
C . Send the new manager a copy of the project charter to ensure the project objectives are understood.
D . Schedule a meeting with the new manager to discuss the business analysis team’s plans.

Answer: B