After executing assessments and workshops, it has been determined that 80% of developments time is related to waiting for responses from various departments. What should the organization do to fix these bottlenecks?
A . Create a global enablement plan. Once each professional has more expertise they will be able to do their job faster and improve the overall productivity.
B . Automate the development and operation process with continuous delivery tools.
C . Create highlyspecialized SWAT teams for requirements management, testing and deployment.
D . Change to a dedicated cells approach, with self-sufficient teams composed of several skills.
Answer: B