After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
A . Implement the change.
B . Approve the test plan.
C . Notify customers.
D . Develop a rollback plan.
Answer: D
Explanation:
The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.