For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product
After collecting the new requirements, what should the project manager do?
A . Assess the impact of the new requirements and initiate the change request process.
B . Work with the product manager and the rest of the team to update the project backlog.
C . Assess the impact and communicate the updated product roadmap to the stakeholders.
D . Follow the change management plan to update the risk register so It accounts for the added scope.
Answer: A