After an Agile Release Train’s first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?
A . Ask Product Management and the System Architect what the new Program Back-log looks like just before the next Innovation and Planning (IP) Iteration, so social-ization can begin
B . Compile all the teams’ objectives from PI Planning and send out a summary report
C . Coach Product Management and the System Architect to include Program Backlog refinement into their cadence-based approach
D . Ask the Lean Portfolio Management function to hold regular Epic review meetings so new Epics will flow to the Agile Release Train
Answer: C