After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.
After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.
This is an example of____________.
A . Qualitative risk analysis
B . Risk Appetite
C . Quantitative risk analysis
D . Risk Tolerance
Answer: C