A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is
planned to start and is due while she is out.
What action should the task owner take?
- A . Set the task condition to At Risk.
- B . Update the Commit Date on the task.
- C . Work on the task and complete it in the given duration.
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?
- A . Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.
- B . Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.
- C . Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.
A client has negotiated a discounted billing rate for video editing in a specific initiative.
How can the project manager override the default billing rate for the Video Editor within a project?
- A . Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.
- B . Add a new billing rate to all tasks that involve video editing.
- C . Add a new billing rate within the project.
Executive stakeholders require both current metric reports and a weekly recap on a project.
How can both needs be met?
- A . Create a program-specific dashboard for the metrics and set up a weekly automated report to send.
- B . Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.
- C . Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.
A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.
What steps should the project manager take to create a custom Workfront report with this information?
- A . Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.
- B . Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.
- C . Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.