The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
- A . A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.
- B . A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.
- C . A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.
A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?
- A . Assigned To
- B . Assignments
- C . Assigned
When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?
- A . Add a custom form
- B . Attach a template to the project
- C . Add tasks
An organization has created unique data fields relevant to their projects. Starting by navigating from a project’s landing page, where is this data found?
- A . Project Details > Custom Forms
- B . Project Details > Overview
- C . Business Case > Project Info
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?
- A . Log a risk as part of the project business case and identify it as a "schedule" risk.
- B . Log an issue on the project and explain that the completion date is at risk.
- C . Create a task in the project and set the Planned Completion Date for 2 weeks.
A team member has five days to complete a critical path task, and the task requires only one hour.
Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?
- A . The next team member cannot start his task.
- B . No impact as the task is not overdue.
- C . The project shows an At Risk automatic condition.
A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.
What should the team lead use to organize these projects to allow them to be tracked together?
- A . Layout template
- B . Program
- C . Group
A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.
How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?
- A . Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A’s access level.
- B . Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.
- C . Share the program with Program Manager A with Manage access and remove Program Manager A’s Manage access on the portfolio.
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?
- A . The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.
- B . The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and
Duration set to 2 weeks. - C . The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
- A . Change the Task Duration Type to Effort Driven
- B . Change the Task Duration Type to Calculated Work
- C . Change the Task Constraint to Fixed Dates
- D . Change the Task Constraint to As Soon As Possible