According to the waterfall cycle approach to systems development, which of the following sequence of events is correct?

According to the waterfall cycle approach to systems development, which of the following sequence of events is correct?
A . Program design, system requirements, software design, analysis, coding, testing, operations.
B . System requirements, software design, analysis, program design, testing, coding, operations.
C . System requirements, software design, analysis, program design, coding, testing, operations.
D . System requirements, analysis, coding, software design, program design, testing, operations.

Answer: C