According to the SAP Activate methodology, in which phase are the scope item Fit-to-Standard workshops executed? Please choose the correct answer.
According to the SAP Activate methodology, in which phase are the scope item Fit-to-Standard workshops executed? Please choose the correct answer.
A . Explore
B. Realize
C. Deploy
D. Prepare
Answer: A