According to the Definition of Done, which activity must be completed for each Sprint?
A . End-user training must be delivered
B . The solution must be built and configured in the development system (DEV)
C . Functionality must be released to the business
D . Functionality must be tested in the production system (PROD)

Answer: B

Explanation:

B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint.

Verified Reference: SAP Activate Project Management Certification Guide, page 114