According to the Definition of Done, which activity must be completed for each sprint? Please choose the correct answer.
A . End user training must be delivered
B . Solution must be built and configured in the development system (DEV)
C . Functionality must be tested in the Quality system (QAS)
D . Functionality must be released to the business
Answer: B