Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means thatA . It is calculated using the original logic.B . It is calculated using logic reflecting out-of-sequence progress.C . An out-of-sequence activity cannot resume until all predecessors are finished.D . There is no such thing.View AnswerAnswer: B

February 19, 2025 No Comments READ MORE +

An early start constraint dictates

An early start constraint dictatesA . An activity's remaining duration.B . The planned start of a successor activityC . The planned start of an activity.D . The actual start of an activity.View AnswerAnswer: D

February 11, 2025 No Comments READ MORE +

Which is NOT an industry-recognized methodology for quantifying critical delay?

Which is NOT an industry-recognized methodology for quantifying critical delay?A . Gantt Chart.B . Periodic Windows.C . Collapsed As-Built.D . Time Impact.View AnswerAnswer: A

February 7, 2025 No Comments READ MORE +

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?A . Estimating remaining durations of activities.B . The correct recording of actual start dates.C . Making "downstream" logic revisions as required.D . Entering the time impacts of delays and...

February 5, 2025 No Comments READ MORE +

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?A . ADM is limited to finish-to-start logic relationships, while PDM is not.B . PDM is a bar chart with network logic, while ADM is a pure logic network.C . ADM is manual CPM...

February 5, 2025 No Comments READ MORE +

Time-scaled logic diagrams are

Time-scaled logic diagrams areA . Only calculated using a computer.B . The same as a pure-logic diagram.C . Used to calculate the most probable activity duration.D . Logic networks that are drawn to match the calendar.View AnswerAnswer: C

January 21, 2025 No Comments READ MORE +