The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:
- A . $328,810
- B . $370,710
- C . $375,658
- D . $378,750
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:
- A . $328,810
- B . $370,710
- C . $375,658
- D . $378,750
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 4, the commodity which experienced the greatest projected percentage price index increase over today is:
- A . None of the above
- B . Manufacturing labor
- C . Steel
- D . Copper
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 4, the commodity which experienced the greatest projected percentage price index increase over today is:
- A . None of the above
- B . Manufacturing labor
- C . Steel
- D . Copper
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
What is the range of unit costs?
- A . $21.57
- B . $26.65
- C . $48.22
- D . $485.00
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Calculate the mean unit cost.
- A . $48.09
- B . $48.22
- C . $48.35
- D . $46.59
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Calculate the mean unit cost.
- A . $48.09
- B . $48.22
- C . $48.35
- D . $46.59
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.
- A . $46.13
- B . $47.63
- C . $48.35
- D . $48.09
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the range of estimated quantities?
- A . $26.78 to $75.00
- B . $485
- C . $45 to $530
- D . $48.22
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the relative frequency of unit costs from Atlanta, GA?
- A . $40.59
- B . 3
- C . $48.33
- D . 33.33%