Exam4Training

A technique to manage load variability would be to:

A technique to manage load variability would be to:
A . apply capacity planning using overall factors (CPOF) to identify priority items at the work center.
B . plan additional safety capacity as a part of total available capacity to meet unplanned demand.
C . design the shop floor with machines that sit idle until additional demand requires their use.
D . use capacity bills to provide a rough-cut method of planning total-time-per-unit value.

Answer: B

Explanation:

Load variability is the fluctuation in electricity demand over time. It is influenced by factors such as weather conditions, time of day, day of the week, and various external events. The higher the load variability, the more challenging it becomes to accurately predict demand and plan capacity1.

A technique to manage load variability would be to plan additional safety capacity as a part of total available capacity to meet unplanned demand. Safety capacity is the act of consistently planning your production below capacity. The reason for this is so the company can become more flexible and responsive to the changing needs of the customer2. For example, if your company was operating at full capacity and your best customer needed extra product, you would be unable to meet their request. By allowing for safety capacity, your company can become more flexible and more responsive.

The other options are not techniques to manage load variability, because they are either irrelevant or ineffective. Applying capacity planning using overall factors (CPOF) to identify priority items at the work center is a simple approach to capacity planning that applies historical ratios. These ratios are based on the master production schedule along with established production standards3. However, this method does not account for load variability or unexpected changes in demand or supply. Designing the shop floor with machines that sit idle until additional demand requires their use is a wasteful and costly way of managing load variability. It does not optimize the utilization of resources or minimize the inventory costs4. Using capacity bills to provide a rough-cut method of planning total-time-per-unit value is a procedure based on the manufacturing production schedule (MPS). It indicates the total standard time required to produce one end product in each work center required in its manufacture5. However, this method does not address the fluctuations in demand or supply that may occur due to load variability.

Exit mobile version