A schedule’s late dates are calculated during the:

A schedule’s late dates are calculated during the:
A . Loop calculations
B . Backward pass
C . Forward pass
D . Float

Answer: B

Explanation:

The backward pass is a technique used in project scheduling to calculate the latest possible start and finish dates for each activity without delaying the project. It starts from the project’s end date and works backward through the network diagram. This calculation helps identify the critical path and determine the amount of float (slack) available for non-critical activities.

Option A: Loop calculations refer to iterative processes within network diagrams but do not specifically relate to late date calculations.

Option C: Forward pass calculates the earliest possible start and finish dates for activities.

Option D: Float is the amount of time that a task can be delayed without affecting the project’s end date, not a calculation method.

Therefore, B. Backward pass is the correct answer as it is used to determine a schedule’s late dates.