A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
A . Project submittal approval process
B . RFI process
C . Payment procedures
D . Punch List process
E . Project start and completion dates
Answer: B, E