A project requires the management system to access a third-party generator set, two smart meters (same model), and two precision air conditioners (same model). How many third-party equipment access fees does the management system need to report?

A project requires the management system to access a third-party generator set, two smart meters (same model), and two precision air conditioners (same model). How many third-party equipment access fees does the management system need to report?
A . 1
B . 3
C . 5
D . None of the above

Answer: B