A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?
A . Ask subject matter experts (SMEs) to provide a detailed plan for each phase.
B . Commit to a detailed global plan from the initiation phase.
C . Get agreement from stakeholders on high-level deliverables and requirements.
D . Request the project management office (PMO) to review the initial plan

Answer: C