A project manager would use a cost breakdown structure to produce:

A project manager would use a cost breakdown structure to produce:
A . the cost of a do-nothing option.
B . an analytical estimate.
C . high-level project costs.
D . a comparative estimate.

Answer: B

Latest APM-PFQ Dumps Valid Version with 354 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments