A project manager would use a cost breakdown structure to produce:
A project manager would use a cost breakdown structure to produce:
A . the cost of a do-nothing option.
B . an analytical estimate.
C . high-level project costs.
D . a comparative estimate.
Answer: B
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments